Building automation in new developments: what to specify

What a developer or design team can write into the tender for building automation in a new building: EPBD functions, an EN ISO 52120-1 class, open protocols, commissioning and handover.

A building outline with a control panel and sensor icons drawn onto the plan

In a new development, a design team can write building automation requirements into the tender documents: the functions the system must perform, the standard and class it must reach, how it talks to other systems, and what is tested and handed over. At EU level the starting point is Article 13 of Directive (EU) 2024/1275, which covers new buildings as well as existing ones, and national law decides how it applies to a given building.

What Article 13 asks of new buildings

Article 13 is a mix of rules for all buildings and rules that apply by size. The paragraphs most relevant to a design team, as read in an English copy of the directive, are these.

  • Paragraph 1: Member States set requirements for technical building systems in new and existing buildings, covering control among other things.
  • Paragraph 3: new buildings are to have self-regulating devices for the separate regulation of temperature in each room (or, where justified, a designated zone), where technically and economically feasible.
  • Paragraph 5: non-residential zero-emission buildings are to have measuring and control devices for the monitoring and regulation of indoor air quality. Article 2 defines a zero-emission building as a building with a very high energy performance, no on-site carbon emissions from fossil fuels, and zero or very low operational greenhouse gas emissions.
  • Paragraph 6: when a technical building system is installed, the energy performance of the altered part is assessed, and the results are documented and passed to the building owner.
  • Paragraphs 9 and 10: a building automation and control system (BACS) in non-residential buildings with heating or air-conditioning rated above 290 kW (31 December 2024) or above 70 kW (31 December 2029), where technically and economically feasible, able to monitor and adjust energy use, benchmark efficiency and detect losses, communicate across manufacturers and, by 29 May 2026, monitor indoor environmental quality.
  • Paragraph 12: zoned automatic lighting controls with occupancy detection on the same thresholds, by 31 December 2027 above 290 kW and by 31 December 2029 above 70 kW.

Paragraph 9 does not separate new from existing buildings in the English copy. How national law applies its dates to a building still being designed is for the national text. Building automation for buildings without a BMS explains the thresholds and why floor area alone does not decide scope.

Pick an EN ISO 52120-1 class for building automation

Article 13, as reproduced in an English copy of the directive, names no efficiency class, so a class would come from a national requirement or from a choice in the brief. EN ISO 52120-1:2022 gives the vocabulary. According to a Buildwise article from Belgium, it grades automation in classes A to D by the control functions reached for each service, with D to be avoided in new buildings, C as the reference and A as high performance with full integration of systems. The same article says authorities can set a minimum class to reach for each new or renovated building. A tender can name a class per service, such as heating, ventilation and lighting, and ask the supplier to show how the design reaches it. The standard is paywalled, so this rests on Buildwise and on an eu.bac guide. That guide notes that the 2022 edition added room-level supply air control based on air quality demand and made the annex on minimum function types normative.

Buildwise also gives a first-pass factor method: a class B office against class C has a thermal factor of 0.80, which Buildwise reads as about 20% savings on heating, cooling and hot water. It calls this an approximation that needs proper commissioning and monitoring to be realized. What to ask before you buy a building automation system has the buyer questions that go with the class.

Specify open protocols and data access

Article 13(10)(c) asks that the system allow communication with connected technical building systems and other appliances, across different technologies, devices and manufacturers. It names no protocol. BACnet is an open standard for building automation (ANSI/ASHRAE 135, ISO designation 16484-5), and BACnet International runs a product certification program, BTL. A specification can require BTL-listed products and a PICS, the manufacturer's statement of a device's BACnet capabilities, for each device. That is a practical suggestion and no legal requirement. An HDR engineer (2023) sees no advantage in a proprietary protocol for new construction. BACnet and Modbus explained for building owners covers the protocols.

Clemson University's building automation standard shows what an owner can write in: open-protocol frameworks that allow interoperability across vendors, point naming that matches the existing system, licensed programming and graphics tools supplied by the contractor, unrestricted access to documentation including passwords and programming tools, and university ownership of all BMS data. Article 16(1) of the directive asks Member States to ensure that owners, tenants and managers can have direct access to their building systems' data, including from building automation and control systems.

Write the indoor environment into the controls

According to the epb.center listing, EN 16798-1:2019 sets requirements for indoor environmental parameters for thermal environment, indoor air quality, lighting and acoustics, as input parameters for designing the building envelope and its heating, cooling, ventilation and lighting. It does not specify design methods. Naming it in the brief gives the controls a target to be tested against, which is a practical suggestion. The brief can also state which rooms get CO2, temperature and humidity sensors and what each sensor controls, since Article 13(10)(d) asks for indoor environmental quality monitoring by 29 May 2026 and paragraph 5 asks for air quality devices in non-residential zero-emission buildings.

For ventilation, the US energy code gives an example of a specification threshold. According to DOE webinar slides on the 2015 IECC, demand-controlled ventilation is generally required where an economizer is present, for zones over 500 square feet with 25 people per 1,000 square feet or more. That is a US code example only. Where to place CO2 sensors for ventilation control covers placement.

Commissioning, documents and handover

ISO 16484-1:2024 covers the project phases of a BACS: design, engineering, installation (installing and commissioning) and completion (handover, acceptance and project finalization). It also sets requirements for as-built documentation and training, and it does not apply to operation and maintenance. ASHRAE describes Guideline 0 as a commissioning process running from predesign through warranty expiration for commissioned systems in new buildings, and Guideline 1.1-2025 as adding technical detail for new HVAC&R systems. ASHRAE Guideline 36-2024 gives uniform sequences of operation for HVAC systems and describes functional tests to confirm them.

Commissioning has a cost and a measured return. Evan Mills's 2009 review of 643 US buildings found, for new construction, a median commissioning cost of $1.16 per square foot, median whole-building energy savings of 13% and a median payback of 4.2 years. These figures cover commissioning in general, which includes more than automation. A REHVA Journal paper on demand-controlled ventilation (2015) says to test and tune in both summer and winter and to review the system after about one year of normal operation. A contract could include that return visit, which is a practical suggestion. Clemson's standard asks the controls contractor to set up typical trends and requires at least 40 hours of training on capital projects. Design for operations and handover data operators wish for cover the handover side.